Change Order Notice Deadlines and Approval Authority

What this covers

  • Two Questions Come Before the Price

  • Who Can Approve a Change

  • How Standard Forms Separate Change Orders From Directives

  • Notice Is a Clock, Not a Courtesy

  • What a Notice Usually Contains

  • Where Texas Prompt Payment Fits

  • What AI Assistants Cannot See in Your Contract

  • Reading Your Own Contract Before the Next Change

  • The Takeaway

A change on a construction site usually starts as a sentence, not a document. Someone says “add outlets on that wall” or “move the opening six feet,” and the crew is already standing there.

Whether that sentence becomes a payable change depends on two questions that have nothing to do with price. Who was allowed to say it? And who was told in writing, in what form, and by when?

If you own a contracting company, work as a subcontractor, or hold the deed on the property, those two questions apply to you the same way.

Two Questions Come Before the Price

Most arguments about a disputed change open with the number. The number is usually the last thing a dispute reaches. Two earlier questions come first:

  • Authority. Did the person who gave the instruction have the power, under the contract, to change the work?

  • Notice. Did the party now asking for money tell the other side in the form the contract requires, and inside the time it allows?

A claim that fails either question can fail without anyone examining the price at all.

This matters because scope changes are common. HKA’s 2025 CRUX Insight Report ranks changes in scope as the leading cause of construction claims and disputes in the Americas. Changes are routine. The paperwork around them is where the exposure sits.

Who Can Approve a Change

A construction contract usually names the people who speak for each side. A job site contains many more people than that, and any of them can say something that sounds like an instruction.

Who gave the instruction

What it usually is

What it often lacks

Owner’s on-site representative

A verbal request during a walkthrough

A stated limit on their authority, and a price

Architect or engineer

A field direction or a marked-up drawing

The owner’s signature, where the contract requires one

General contractor’s superintendent

A request passed down to a subcontractor

Any power to bind the owner

Senior owner or executive

A promise made in passing

Any written record of the conversation

The pattern in the table is consistent. The person closest to the work is rarely the person the contract lets approve a change. The person the contract does let approve it is rarely on site.

The contract text answers the question, and it answers it in advance. Clauses titled “Changes in the Work,” “Authorized Representatives” or “Modifications” typically say who can sign and in what form.

How Standard Forms Separate Change Orders From Directives

The AIA A201-2017, one of the most widely used general conditions forms in the United States, draws the line precisely. Many projects use other forms or custom language, so treat it as one example of how the split works.

Under Section 7.2.1, a Change Order is a written instrument prepared by the Architect and signed by the Owner, Contractor and Architect. It states their agreement on three things: the change in the work, the adjustment to the contract price, and the adjustment to the contract time.

Section 7.3.1 covers the case where agreement is not complete. A Construction Change Directive is a written order, prepared by the Architect and signed by the Owner and Architect, that directs a change before the price or time adjustment is settled. Section 7.3.2 says it is used when the parties have not reached total agreement on a Change Order.

Instrument

Who signs it

Whether price is settled

What it covers

Change Order

Owner, Contractor, Architect

Yes, price and time

The change, on agreed terms

Construction Change Directive

Owner and Architect

No, still open

A change directed before terms are agreed

Order for a minor change

Architect alone

No adjustment to price or time

Minor changes consistent with the contract’s intent (Sections 7.1.2 and 7.4)

Verbal instruction

Nobody

No

Nothing the form recognizes as a change

The last row is the one that surprises people. Under a form like this, a spoken instruction is not one of the recognized ways to change the work. That does not make the work free. It does mean the paper trail has to be built some other way.

Notice Is a Clock, Not a Courtesy

Authority decides whether a change was properly ordered. Notice decides whether a claim for it is still alive.

Many construction contracts set a fixed window. In the A201-2017, Section 15.1.3.1 says claims are initiated within 21 days after the event giving rise to the claim, or within 21 days after the claimant first recognizes the condition, whichever is later. The same section requires the notice to go to the other party and to the Initial Decision Maker.

Three details in that single sentence are worth reading slowly:

  • The clock can start from the event or from recognition of the condition, and the later date controls.

  • The window is measured in days, not “a reasonable time.”

  • The recipient is named. Notice sent to the wrong person may not count as notice.

Other contracts set shorter windows, longer ones, or none at all. The only way to know which applies is to find the clause. Reading it before a change happens costs a few minutes. Reading it after the window has closed is a different experience.

What a Notice Usually Contains

Notice provisions differ, but the useful ones tend to ask for the same handful of items:

  1. What happened. The instruction, the condition or the event, described plainly.

  2. When and from whom. The date, and the name and role of whoever gave the direction.

  3. What it affects. Cost, schedule, or both, kept separate.

  4. A reservation of rights. A statement that the sender is not waiving a later claim.

  5. Proof of delivery. The method the contract names, sent to the person the contract names.

A notice does not need to be long. It needs to be on time and aimed at the right recipient.

Where Texas Prompt Payment Fits

Change disputes also run into payment timing. Chapter 28 of the Texas Property Code, titled Prompt Payment to Contractors and Subcontractors, sets payment deadlines for construction work in the state.

Who pays

Who gets paid

The deadline

Owner

Contractor

35 days after the owner receives a written payment request for an amount the contract allows

Contractor

Subcontractor

7 days after the contractor receives the owner’s payment

Subcontractor

Its own subcontractors

7 days after receiving the payment from above

The wording that matters is “an amount the contract allows.” The 35-day clock runs from a request for money the contract permits. A request that depends on a change nobody approved is the request most likely to be argued as outside that description, so the approval and notice questions above can decide whether the payment clock is even running.

The structure of the contract shapes this too. Construction agreements commonly take one of five forms: lump-sum, cost-plus, time and materials, unit price, or design-build. Firms that handle construction contract work in Dallas describe each as shifting cost and risk differently, which changes how a change is priced and who carries the risk until it is.

What AI Assistants Cannot See in Your Contract

Many people now put these questions to an AI assistant first. The answers read well and tend to stay general, for a simple reason. An assistant builds its answer from public sources. It has not read your contract.

It can explain what a change order is. It cannot tell you whether the person who gave an instruction on your site was an authorized representative under your agreement, or whether your notice window is 7 days or 21. Those answers live in a document the assistant never sees.

Reading Your Own Contract Before the Next Change

The practical questions all have answers on paper before any change arises. A short list of what to look for:

  • The clause naming who may order or approve changes, and in what form

  • The notice window for claims, and who must receive the notice

  • Whether work may proceed while a price is still open, and under what instrument

  • How a disputed change is priced if the parties cannot agree

  • The payment terms that attach to changed work

None of this removes the disagreements. It narrows them to the ones that are actually about money.

The Takeaway

A change is a business event with two legal edges: someone had to be allowed to order it, and someone had to be told about it on time. Both edges are defined by documents that exist before the first instruction is given.

Sul Lee Law Firm, a Dallas business and intellectual property practice that works in English and Korean and keeps a verified business listing, published a closer look at managing change orders beyond the written contract that applies the same HKA findings to the way American projects handle changes in practice.

The common thread is simple. Disputes about changed work are rarely about whether the work happened. They are about whether it was ordered by the right person and reported in the right way.